CEO PJBS VISIT PLTMG BAWEAN

16.07.2014
|
0 Comments
|
BAWEAN 2

This post is also available in: Indonesian

BAWEAN – To ensure operation readiness PLTMG Bawean 3×1 MW unit on the 24th till June 25, 2014 conducted by the visit Monoarfa Day, Director of PJBS along with General Manager of PT PJB Unit CNG & LNG Plant Project Edy Dwi Hartono and Cahyono, Manager of PT PLN East Java. Process Planning, Procurement and Construction of 3×1 MW PLTMG Bawean is carried out by trained professional staff PJBS starting in November 2013 and was completed in May 2014. Commissioning Phase will be conducted on July 4, 2014 until the date of July 15, 2014, is expected to visit is very useful for ensure that the project Operation and Maintenance performed by PJBS will be running smoothly and ensure that supplay GAS always be fulfilled. (Pras-PJBS)